Specialty Boiler Rigging

![]() | ![]() | ![]() | ![]() | ![]() |
Specialty boiler rigging in North Carolina at UNC Chapel Hill. Due to traffic and logistics this job was completed over the course of one weekend with coordination with UNC and the Chapel Hill Police Department.
Weight: 125,000 lbs
Dimensions: 46' Long X 14'6" Wide X 19'6" Tall (21'6" Tall on the trailer)
The boiler was offloaded at the rail spur with our 400 ton gantry system and then transported to the site. Once onsite the boiler was offloaded with our 500 ton crane and set on the rigging sled system. The boiler was then moved into place. Once in place the gantry system was used again to lift off of the sleds and set into place.